Cut-Off Wall for Pumping Station near HIA, Qatar
Abu Hamour Surface and Ground Water Tunnel Project is one of the key drainage projects being implemented by Ashgal for upgrading Qatar’s drainage network. The tunnel runs from Abu Hamour to a pumping station planned at the coast near the Hamad International Airport. Ammico’s scope involved construction of a plastic bentonite-concrete cut-off wall to prevent lateral ingress of ground water during excavation for the pumping station.
Project Data Sheet
Ammico scope of works include supply and installation of Marine Pilling Works for Glulam Beam & Wooden Decking and Steel Tubular piles.
Work Description | Unit | Quantity |
Installation of marine piles of diameter 900 mm. | No | 48 |
Length | m | 15.1 |
Diameter | mm | 22.5 |