Abraj Quartier 3, 4, 5 & 6, The Pearl Qatar

Abraj Quartier 3, 4, 5 & 6, The Pearl Qatar

The project is located in the Pearl, Qatar with a total plot area of 60,000m2. Development included four towers, each with one basement and forty storeys. Ammico’s scope comprised of installation of contiguous wall and CSM wall (with steel profiles as earth retention system followed by excavation from existing ground level to an average bulk excavation depth of approximately 7.0mand associated dewatering works in addition to installation of 364 nos. bored cast in-situ working piles with diameter of 1500mm.

YEAR: 2014
Plot Area: 60,000 m2
Client: AKY Real Estate

Work Description

nit

Quantity

Contiguous wall 800mm @ 850mm 12m deep

m

880

CSM wall 640mm with beams as retaining wall

m

127

CSM wall 640mm without beams as cut-off wall

m

418

Working piles of 1500mm dia.

Nos.

364

Excavation

m3

340,000

Dewatering

m2

60,000