Abraj Quartier 3, 4, 5 & 6, The Pearl Qatar

Abraj Quartier 3, 4, 5 & 6 – The Pearl, Qatar

The project is located in The Pearl, Qatar, with a total plot area of approximately 60,000 m². The development comprises four towers, each consisting of one basement level and forty storeys.

Ammico’s scope of work included the installation of a contiguous wall and a Cutter Soil Mixing (CSM) wall incorporating steel profiles as the earth retention system, followed by bulk excavation from the existing ground level to an average depth of approximately 7.0 m. The works also included associated dewatering activities and the installation of 364 bored cast-in-situ piles, each with a diameter of 1,500 mm and between 16 to 18 meters deep.

Work Description Unit Quantity
Contiguous wall 800mm @ 850mm 12m deep m 880
CSM wall 640mm with beams as retaining wall m 127
CSM wall 640mm without beams as cut-off wall m 418
Working piles of 1500mm dia. Nos. 364
Excavation m3 340,000
Dewatering m2 60,000
CLIENT

AKY Real Estate

MAIN CONTRACTOR

KEO International Consultants

LOCATION

The Pearl – Doha, Qatar

SOLUTIONS

Shoring Piles

START DATE

March 2014

COMPLETION DATE

December 2015