Sheraton Park Project involves construction of a park in West Bay Doha with four levels of underground car parking. The projects covers an area of about 80,000 m2
Ammico’s scope comprised of installation of secant piles and contiguous piles for earth retention, shotcreting and rock bolting at parts of the excavation, and deep excavation and disposal works to the tune of about one million cubic meters.
Project Scope
Work Description | Unit | Quantity |
---|---|---|
Secant wall 800 mm @ 700 mm c/c | m | 605 |
Contiguous wall 800 mm @ 850 mm c/c | m | 241 |
Excavation | m3 | 1,000,000 |
Shotcrete and rock bolting |